2024

Construction report April 2024

30.042024

Despite the capricious weather in April, construction is progressing dynamically at the Waterside Residence!

The base plate assembly concreting is 100% completed on the buildings of the Danube-bank residential park.

The formwork of the slab above the 1st floor has already been completed and all the structures below have been built on the “A” building.

On the “D” building, the integration of the slab cooling-heating ceiling panels above the 1st floor into the structure and the concreting have been completed.

The foundation slab was concreted in 2 phases on building “B” and in 3 phases on building “C” and the construction of the basement level structure began.

Keep following along as we share how we develop your future home!

Contacts

Main office+36 1 700 2500

BUDAPEST, SZABADSÁG TÉR 7, 1054 Bank Center, Platina I. tower, 3rd floor 10:00 - 18:00

  • Linkedin