Construction Report, December 2024, Parkville Residences

2024.12.18

By early December, the diaphragm wall had been fully enclosed and was completely finished. Of the ground anchors supporting it, 41 have been tensioned; only 9 remain to be drilled and tensioned.

Earthwork has begun on the Nádasdy Street side, and the area has been prepared for the next phase of work: pile driving. The installation of the steel reinforcement for the final short section of the header beam is also underway.

We’ll provide another update on the construction progress next month—follow our social media channels for the latest videos!

Would you like to move into our residential complex? Request a personalized offer from our team:

+36 1 700 4433

sales@parkville.hu

Contacts

Intergal Group értékesítési iroda, Bank Center

Main OFFICE

+36 1 700 2500

1054, BUDAPEST, SZABADSÁG TÉR 7, BANK CENTER, PLATINA I. TOWER, 3RD FLOOR

10:00 - 18:00

Enter your details and the manager will contact you as soon as possible or you can also contact our sales department+36 1 700 2500
Last name*
First name*
Phone
*
Email*

By clicking the "Send the application" button, you agree to the processing of personal data