Construction Report, December 2024, Parkville Residences

By early December, the diaphragm wall had been fully enclosed and was completely finished. Of the ground anchors supporting it, 41 have been tensioned; only 9 remain to be drilled and tensioned.
Earthwork has begun on the Nádasdy Street side, and the area has been prepared for the next phase of work: pile driving. The installation of the steel reinforcement for the final short section of the header beam is also underway.
We’ll provide another update on the construction progress next month—follow our social media channels for the latest videos!