Construction report March 2024
The construction is progressing dynamically, and according to the latest developments, the following activities are underway:
Several significant steps have been taken on the construction site recently. The installation of the geothermal mechanical system beneath the foundation slabs has reached 100% completion. Additionally, the construction of Building “B” has commenced, with the first phase of the foundation slab already poured.
Following excavation work on Building “C,” the construction of the elevator shaft and other recesses has begun, while on Building “D,” the construction of the ground floor ceiling and transformer rooms has been completed.
In Building “A,” the vertical structures on the ground floor are fully formed, and in the area of basement and ground floor garage space has been completed (nearly 900 m²).
We appreciate your continued interest! Please continue to follow us on the exciting journey of construction, and we will provide further updates soon!