Construction report November 2024

02.122024
Már a 4. emeleten járunk a falazással.

Construction continued to progress dynamically at Waterside Residence in November.

The masonry of buildings 'A' and 'D' was completed on the 1st and 4th floors. The mechanical and electrical work on building A is in progress and basic electrical and mechanical installation has started on building ‘D’.

On buildings ‘B’ and ‘C’, the 1st floor walls are finished. On 'C' building, the masonry work on the 2nd floor is already underway, which is also being has just started.