2024

Construction report September 2024

30.092024
Even the floods did not stop the construction!

In September, despite the flooding and rainfall, construction of the Waterside Residence continued to progress well. Although the complex is being built in the immediate vicinity of the Danube, it is located just outside the floodplain. The buildings remained dry during the flood, with only rain soaking the still open parts.

The slab above the 6th floor of building A is already under construction, and the masonry work on the 1st and 2nd floors is already underway.

In building B, the 4th floor pillars and walls are being built.

In building 'C', after the preparation of the slab above the 3rd floor, the concreting will start.

In building 'D', the formwork works for the slab above the 7th floor are underway and the construction of the facade, partition and partition walls has started.

Follow the construction progress month by month on our website, social media platforms and Youtube!

Request a personalised quote from our colleague:

📞 +36 1 700 2500

✉️ sales@waterside.hu

Contacts

Main office+36 1 700 2500

BUDAPEST, SZABADSÁG TÉR 7, 1054 Bank Center, Platina I. tower, 3rd floor

  • Linkedin