May progress report on the construction project

Construction at Waterside Residence is moving forward at a rapid pace this May as well!
The foundation slabs for the buildings in our marina-front residential complex are 100% complete! The vertical structure for the 2nd floor of Building ‘A’ and the ground floor of Building ‘B’ is currently under construction. On Building ‘C,’ the floor slab above the basement is being constructed, while on Building ‘D,’ the floor slab above the second floor is being built. In the underground parking garage area, the floor slab above the basement has been completed on the sections facing Hajókovács and Túróc Streets, and the formwork for the floor slab above the basement is already in place in the central area.
Would you like to move in? Our colleagues will be happy to help you choose the home that best suits your needs!
In the meantime, follow the rapid progress of the construction project month by month on our website!