2025

Construction report 2025 February Waterside Residence

2025.02.28

As of mid-February, the monolithic framework of sections A, B, C, and D has been fully completed. Work on the site continues at a steady pace, strictly following the schedule and plans.

Wall masonry in sections A and D has been completed, while in sections B and C, it has reached the fourth floor.

Key engineering and electrical installation works are actively underway in all sections of the complex. At the same time, window installation has begun on the first two floors of section A.

In the basement and ground floor, electrical and mechanical systems are being installed, and brick masonry is now 50% complete.

Discover premium living at Waterside Residence! Contact our expert team today and let us help you find your dream home.

https://intergal-group.hu

+36 1 700 2500

 sales@waterside.hu

Contacts

Main OFFICE

+36 1 700 2500

1054, BUDAPEST, SZABADSÁG TÉR 7, BANK CENTER, PLATINA I. TOWER, 3RD FLOOR

10:00 - 18:00

Enter your details and the manager will contact you as soon as possible or you can also contact our sales department+36 1 700 2500
Last name*
First name*
Phone
*
Email*

By clicking the "Send the application" button, you agree to the processing of personal data