2025

Construction report 2025 July Parkville Residences

2025.08.04

Building A

Concrete has been poured on one half of the parking level, where the pillars and walls are next, and the other half is now being shuttered and ironwork is being installed.

Building B

The 3rd tower spire has also been put in place, so we can move ahead even faster

Building C

In July, the 1st floor was completed and the cooling and heating panels for the apartments were installed.

Building D

The ground floor has been concreted, the first floor formwork is under construction and some of the wall panels are in place.

Choose the home of your dreams from the Parkville Residence!

Ask our colleagues for a personalised offer:

https://intergal-group.hu

+36 1 700 3507

sales@parkville.hu

Contacts

Main OFFICE

+36 1 700 2500

1054, BUDAPEST, SZABADSÁG TÉR 7, BANK CENTER, PLATINA I. TOWER, 3RD FLOOR

10:00 - 18:00

Enter your details and the manager will contact you as soon as possible or you can also contact our sales department+36 1 700 2500
Last name*
First name*
Phone
*
Email*

By clicking the "Send the application" button, you agree to the processing of personal data