Construction report 2025 March Waterside Residence

2025.03.31

Just like in nature, spring has brought remarkable changes to the Waterside Residence construction site. Throughout March, work continued on schedule and as planned, with key milestones successfully reached.

Masonry work on Buildings A, B, C, and D has progressed significantly, with the frame infill, partition, and separation walls now completed on all floors. Sealing and mansory of shafts have begun in Building A.

The basic electrical and mechanical installations in the apartments of Buildings B, C, and D are ongoing, while the corridor electrical installations in Building A have been fully completed.

In Buildings A and D, the installation of façade windows and the vapour barrier insulation on the roofs are currently underway.

Meanwhile, in the basement and ground floor, construction of electrical and mechanical tracks is still in progress, while the masonry work has been fully completed.

Find your premium home at Waterside Residence in Marina Part!

Contact our team for a personalized consultation:

https://intergal-group.hu

+36 1 700 3507

sales@waterside.hu

Contacts

Main OFFICE

+36 1 700 2500

1054, BUDAPEST, SZABADSÁG TÉR 7, BANK CENTER, PLATINA I. TOWER, 3RD FLOOR

10:00 - 18:00

Enter your details and the manager will contact you as soon as possible or you can also contact our sales department+36 1 700 2500
Last name*
First name*
Phone
*
Email*

By clicking the "Send the application" button, you agree to the processing of personal data