Construction report 2025 September Parkville Residences

Structural work continues to dictate the pace of the Parkville project.
This month, we completed the excavation work, and the concrete work on the ground floor of the last section of Building B was finished. Work continues on the stairwell and elevator shaft, as well as concrete finishing work in the basement levels.
In Building A, the ground floor walls and pillars have been completed, and the electrical contractor and ceiling cooling/heating panels are already installing the necessary fittings in the floor slab above the ground floor.
The vertical structures of the first floor of buildings C and D have been completed, the formwork for the second floor of building C has been assembled, the electrical and panel contractors have already completed the necessary installations here, and steel installation has begun.
In building D, the second floor has been concreted, taking the project to new heights.