Construction report 2025 July Parkville Residences

04.082025

Building A

Concrete has been poured on one half of the parking level, where the pillars and walls are next, and the other half is now being shuttered and ironwork is being installed.

Building B

The 3rd tower spire has also been put in place, so we can move ahead even faster

Building C

In July, the 1st floor was completed and the cooling and heating panels for the apartments were installed.

Building D

The ground floor has been concreted, the first floor formwork is under construction and some of the wall panels are in place.