Construction report 2025 July Waterside Residence

31.072025

Building A: Tiling works have begun on the lower floors. On the upper levels, apartment painting, screed concrete flooring, and mechanical plastering are in progress. The vapor barrier insulation has been completed on the rooftop, the drainage outlets have been installed, and both waterproofing and thermal insulation are currently underway.

Building B: All brickwork has been completed, including shaft masonry. Mechanical plastering of the interior walls has started, along with thermal insulation of the facade and balconies. Screed concrete work is progressing on the 5th and 6th floors.

Building C: Brickwork and rooftop vapor barrier insulation have been completed. Facade doors and windows have been installed, and shutter installation is currently in progress. Insulation work on the facade and balconies has also begun.

Building D: Screed concrete and mechanical plastering works have been completed on the lower floors. The rooftop vapor barrier insulation has been installed, and all facade doors and windows are in place. The transformer rooms have also been completed.

The construction has now entered an impressive new phase, and each building is rapidly approaching its final form.

Choose your premium home at Waterside Residence, right on "Marina-part". Our sales team is ready to help you find the perfect new home!

+36 1 700 3507 sales@waterside.hu intergal-group.hu

Contacts

Main office+36 1 700 2500

BUDAPEST, SZABADSÁG TÉR 7, 1054 Bank Center, Platina I. tower, 3rd floor 10:00 - 18:00

  • Linkedin