Construction report 2025 November Parkville Residences

2025.11.27
Parkville Residences építési jelentés 2025. november

Parkville Residences – new specialized work at the Parkville construction site!

The masonry contractor has started bricklaying work on the ground floor and is progressing towards Building A. At the same time, the building electrical contractor has started work on the P2 basement level.

Building A:

The second floor has been concreted, and formwork and mechanical and electrical work is underway on the third floor. Structural engineers are finishing the concrete work on the ground floor apartments and storage rooms.

Building B:

The first floor has been concreted, and formwork and mechanical and electrical work is underway on the second floor.

Building C:

The third floor has been concreted, and formwork and mechanical and electrical work is underway on the fourth floor.

Building D:

The floor of the 4th floor has been concreted. This is currently the highest point of the project. The chimney contractor will arrive after the next slab has been completed.

Choose your dream home from the Parkville Residences apartment selection!

Ask our colleagues for a personalized offer:

https://intergal-group.hu

+36 1 700 3507 sales@parkville.hu

Contacts

Main OFFICE

+36 1 700 2500

1054, BUDAPEST, SZABADSÁG TÉR 7, BANK CENTER, PLATINA I. TOWER, 3RD FLOOR

10:00 - 18:00

Enter your details and the manager will contact you as soon as possible or you can also contact our sales department+36 1 700 2500
Last name*
First name*
Phone
*
Email*

By clicking the "Send the application" button, you agree to the processing of personal data