Developments in the Construction in April – Waterside Residence
Despite the capricious weather in April, construction is progressing dynamically at the Waterside Residence!
The base plate assembly concreting is 100% completed on the buildings of the Danube-bank residential park.
The formwork of the slab above the 1st floor has already been completed and all the structures below have been built on the “A” building.
On the “D” building, the integration of the slab cooling-heating ceiling panels above the 1st floor into the structure and the concreting have been completed.
The foundation slab was concreted in 2 phases on building “B” and in 3 phases on building “C” and the construction of the basement level structure began.
Keep following along as we share how we develop your future home!