November Progress Report on the Parkville Residences Construction Project

2024.12.05
Novemberi építkezés Parkville Residences

Construction continued at a brisk pace at the Parkville Residences residential complex.

By the end of November, 93% of the diaphragm wall work had been completed, and in connection with this, work began as early as the second week of November on installing the temporary anchors required prior to earthwork. By the end of the month, a total of 32 anchors had been drilled and 7 had been tensioned. Construction of the header beam required for the continuation of the structure is 35% complete. In November, on-site discussions began with the contractor

responsible for the geothermal borehole and regarding the earthworks necessary for the pile driving scheduled to begin in January 2025.

Curious about how your dream home is taking shape? Follow the construction day by day on our live cameras:

https://www.youtube.com/@IntergalGroup

Interested in buying a new home? Contact our team and request a personalized offer:

+36 1 700 4433

sales@parkville.hu

Contacts

Intergal Group értékesítési iroda, Bank Center

Main OFFICE

+36 1 700 2500

1054, BUDAPEST, SZABADSÁG TÉR 7, BANK CENTER, PLATINA I. TOWER, 3RD FLOOR

10:00 - 18:00

Enter your details and the manager will contact you as soon as possible or you can also contact our sales department+36 1 700 2500
Last name*
First name*
Phone
*
Email*

By clicking the "Send the application" button, you agree to the processing of personal data