Waterside construction reaches an important milestone

2025.01.28

Construction is progressing steadily, and we have reached an important milestone. Sections A and D are now structurally complete, and we can soon say the same about Sections B and C.

Section A: The masonry work on floors 1 to 7 has been completed. The basic mechanical and electrical installations are currently in progress.

Section B: The masonry work on floors 1 and 2 is also complete, and work is continuing on the 3rd floor.

Section C: The wall construction on the 1st and 2nd floors is complete.

Section D: The masonry work on floors 1 to 7 has been completed, and the basic mechanical installations have started.

Work on the electrical and mechanical installations in the basement and ground floor is currently underway.

Pick your dream home at Waterside Residence! For more information, please contact our colleagues:

watersideresidence.hu

+36 1 700 2500

sales@waterside.hu

Contacts

Main OFFICE

+36 1 700 2500

1054, BUDAPEST, SZABADSÁG TÉR 7, BANK CENTER, PLATINA I. TOWER, 3RD FLOOR

10:00 - 18:00

Enter your details and the manager will contact you as soon as possible or you can also contact our sales department+36 1 700 2500
Last name*
First name*
Phone
*
Email*

By clicking the "Send the application" button, you agree to the processing of personal data