The foundation works of the Parkville Residences are progressing at a fast pace!

06.012025

By the beginning of December, the slotted wall was fully enclosed and completed. The ground anchors supporting it are 41

have been tightened and only 9 more need to be drilled.

Earthworks have started on the Nádasdy Street side of the site and the area has been prepared for the next phase of work, the piling. Iron installation of the final short section of head beam is also underway.

We will continue to report on the construction progress next month, follow our social media channels for the latest videos!